
Monthly Update
April 2008
Robin Maddock
Restoration moved on apace during April and thankfully the weather did not hold
us up.
The roofs on both buildings are almost complete with the new ridge tiles for the
roof of the main building now on site and will be installed shortly.
With the weather being kind to us, the replacement of the harling went very
smoothly. All the base coats are now completed and it makes a tremendous
difference to the appearance of the building. The lime wash coats will be
applied mid and end-May and due to the traditional process and materials used
this will result in very low maintenance work and costs.
In the first floor community space, all the repointing of the stonework has been
completed, where this was necessary and it makes this interior space very
impressive. New windows and external louver shutters have also been installed
and now that natural light can get into this area, the effect is stunning. The
toilets in the community space have been framed out and clad with the sanitary
ware being fitted towards the end of May.
Down in the ice chambers, a detailed examination of the barrel-vaulted roofs has
revealed that they are in excellent condition and will need hardly any
repointing, just a clean up.
Work has started in the 2 and 3rd ice chambers to lift some of the cobbled floor
so that trunking can be laid for the electricity supply for lighting the various
displays. This has proved to be a laborious task because under the cobbles was
solid rock in some places. At least the building's foundations are "rock solid!!
Power and telecoms cables have been put into the first floor community space in
the main building and will be installed in the office a genealogical research
centre in the coming weeks. Designs for these areas are now complete and work
will commence this week to lay the floor and fit them out.
In the last newsletter I mentioned that we were now looking at a ground source
heating system for the building. Our options were to either lay 800 metres of
pipes in the ground outside the bothy and across the road in the net drying
area, or sink 2 boreholes. Due to the nature of the ground with solid rock just
below the surface in many places, we are being forced to sink boreholes. Whilst
the capital cost of this type of installation is significantly more than the
budgeted cost for a fossil fuel system, the running and maintenance costs will
be significantly less and it will help to reduce our carbon emissions and carbon
footprint. We are currently examining the financial implications as a matter of
urgency.
Research for the displays in the ice chambers is going well with our
professional researcher uncovering some significant pieces of information about
Portsoy's history and the bothy. This will make for very exciting and
educational displays.
There is probably some slippage from the end-May completion date, but only by a
week or ten days. However, it will be ready for the official opening on Saturday
21st June, the first day of this year's Scottish Traditional Boat Festival.
Some more pictures of the building showing its current state can be found by
clicking HERE
